We decided on a two year timeline for the project. I came up with a general plan and am posting it here mainly as a point of reference, as I'm sure it will change (and has already changed) as the project continues

Year One (Summer/Fall 2007)
  1. Mid June - Clean up heavy dumping
  2. By last week in June - Mow down high grass on site
  3. Saturday, June 30 - Clean Up Day
  4. Early July - Site Preparation including spraying herbicide
  5. Mid July/August - Construction of Path
    · Purchase of 4 foot wide landscape fabric (enough for double layer
    · Mark out Path
    · Level the area
    · Installation of fabric and wood chips
  6. September - Site Preparation including spraying herbicide
  7. Ongoing - Monitor Site for Dumping

Year Two (Spring/Summer 2008)

  1. Mid May - Determine if site needs another spraying of herbicide
  2. Late May - Plant Natives
    - May purchase seeds with ’07 funds
  3. Ongoing
    · Maintenance of Natives and maintenance of path